Project Schedule:
Sceideal an Tionscnaimh:

Time frame for the project is as follows:

  Schedule Date
  Constraints Study June 2001(completed)
  Preferred Route Corridor Nov 2001 (completed)
 

Publish Compulsory Purchase Order (CPO)

Dec 2003(completed)
  Publish Environmental Impact Statement (EIS) Dec 2003(completed)



The Project Team must submit the EIS, CPO to An Bord Pleanála for approval, prepare contract documents
and invite tenders for design & build.

     
  Schedule Date
  Oral Hearing Mar/Apr 2004 (completed)
  Decision by An Bord Pleanála 30th July 2004
  Design & Build tender process

2006 (completed)

 

Construction Phase

     
  Schedule Date
  Construction start Nov 2006 (underway)
  Construction finish December 2009