Choosing a Route:
Bealach a Roghnú:

The Limerick Southern Ring Road Phase II will be a grade separated dual carriageway with interchanges to existing and proposed roads, a river crossing of the Shannon and other structures such as overbridges, underbridges and link roads as required to access the existing road network.

Phase II is a continuation of the existing Southern Ring Road project and will extend the Phase I section to join the N20 to the N18. This scheme will complete the Limerick Southern Ring Road and link all the national roads coming into Limerick:

N18 Ennis Road
N69 Dock Road from Foynes
N20 / N21 Cork / Kerry Road
N24 Tipperary Road
N7 Dublin Road

Choosing a Route
Crossing the Shannon
Constraints Study
Route Selection
Crossing Selection
CPO/EIS
CPO Confirmation
Award of PPP Contract

Road Network
Mapping is based on Ordinance Survey Ireland by permission of the Government Licence No. NE0002301
© Government of Ireland.

The Project Steering Committee has engaged Consultants MC O'Sullivan & Company Ltd and COWI of Denmark to assist them in

  • Evaluating the need for the scheme
  • Recommending a route for the new road
  • Identifying land required for the scheme
  • Satisfying the requirements of the NRA National Roads Project Management Guidelines, phases 2, 3 and 4
    • Constraints Study - completed. A Constraints Study has been carried out to determine any physical, procedural, legal, environmental constraints that could affect the design or delay progress and influence the cost of the scheme.
    • Route Selection.
    • Preliminary Design / Compulsory Purchase Orders (CPO) / Environmental Impact Statement (EIS) - sufficient design will be carried out to allow CPO to proceed and an EIS to be prepared.